How to Build a Gravel Driveway, Layer by Layer
By Ali (not a contractor)Updated
A gravel driveway is built in three compacted layers: 4 to 8 inches of large crushed stone (#2) at the bottom, 2 to 4 inches of #57 stone in the middle, and 2 to 4 inches of #8 stone or crusher run on top. You dig out as deep as the stone is thick: 4 to 8 inches for cars on firm ground (6 is common), 8 to 12 inches for trucks or soft soil. A 12 by 60 foot driveway built 12 inches deep takes about 29 cubic yards, roughly 42.5 tons, with 10 percent extra for settling.
The three layers
A gravel driveway has three layers: a 6 in base of #2 stone, a 3 in middle of #57 and a 3 in top of #8 or crusher run, typical thicknesses after compacting. Each layer gets its own stone so the pieces lock together and water still drains.
| Layer | Stone and size | Thickness |
|---|---|---|
| Base | #2 stone, 1½ to 2½ in | 4 to 8 in (6 typical) |
| Middle | #57 stone, 1 in down to 3/16 in | 2 to 4 in (3 typical) |
| Top | #8 stone (about 3/8 in) or crusher run | 2 to 4 in (3 typical) |
The base carries the wheel load and drains. The middle layer stabilizes the base and passes water down. The top is the smooth surface you drive on, and it packs tight (Port Aggregates, Bray Topsoil and Gravel).
Suppliers differ on thickness. For heavy use, Port Aggregates gives 6 to 8 inches of base and 2 to 3 inches each above it, and Hello Gravel’s layer guide gives 4 to 6, 4 to 6, then 2 to 4. A split of 6, 3 and 3 is a fair middle path, and it is where the gravel calculator’s driveway presets start.
Check the units in other guides. Standard #2 stone is 1½ to 2½ inches across, and #1, the largest standard crushed grade, tops out at 3½. A base described as 4 to 6 inch stone, or 6 inch crushed rock, is almost certainly quoting layer thickness.
How deep to dig
The stone sits in the trench, so dig depth equals the total depth of all the layers. Strip the grass, roots and topsoil first. Topsoil left under the stone compresses unevenly and leaves soft spots (Komplet America).
| Use | Dig depth | Layers |
|---|---|---|
| Cars, firm soil | 4 to 6 in | Two: base, then #57 or surface stone |
| Pickups, deliveries, soft or wet soil | 8 to 12 in | All three |
| Clay, deep frost, heavy equipment | 12 to 18 in | All three, plus fabric |
For light residential use, Port Aggregates says 4 to 6 inches total, Hello Gravel and Gravelshop say 6 to 8, and Komplet says 6 to 10. The gravel calculator’s light-use driveway preset spans 4 to 8 inches and starts at 6, so go deeper if your soil is soft. For heavier loads Port says 8 or more, Gravelshop says 8 to 12, and Hello Gravel’s layer guide says 12 to 18. Clay calls for the deep end (BaseCore).
Fabric under the stone
Geotextile is the woven or non-woven fabric sold for driveways. It lies on the soil under the first layer and keeps wet, fine soil from pumping up into the gaps between stones (FHWA, Bovee’s). Use it on clay, silt, wet ground, or soil that goes soft in spring thaw. On dry, firm ground it is optional (Komplet America).
Buy driveway-grade fabric, since Bovee’s says garden landscape fabric is the wrong product. Overlap seams at least 12 inches, and 18 to 24 on soft ground (Bovee’s, Pro Fabric Supply). Keep at least 6 inches of stone above it, and 8 to 12 on soft ground (Pro Fabric Supply, Mainline Materials).
Compaction
Build in lifts and compact each one before adding the next. Spread 4 to 6 inches of loose stone per lift (Hello Gravel, Bovee’s). A plate compactor on a thicker pile only packs the top 4 to 6 inches and leaves loose stone below (Bovee’s). A 6 inch compacted base needs a little over 6 inches of loose stone, so it goes down in two lifts.
A plate compactor or a vibratory roller both work (Hello Gravel). Komplet America says a plate compactor handles small areas and a roller is standard on clay soil. If you can, compact the bare soil before the fabric goes down (Pro Fabric Supply).
Stone settles as it packs. Bob Vila adds 4 percent, Komplet America says clean open-graded stone loses 5 to 10 percent, and a Capitol Flexi-Pave spec sheet puts #57 near 8 percent. The calculators’ “Extra for settling” box, under Prices & extras, starts at 10 percent for #57, crushed stone and crusher run. Crusher run settles more than clean stone, so ask your supplier what the top layer needs.
Crown and slope
Shape the driveway so the middle is higher than the edges. Water that sits in tire tracks softens the base, and a flat or cupped surface holds it (Hunker, Penn State). The usual crown is a half inch of fall per foot from the center to each edge (Hunker, Bovee’s), and Penn State allows up to three quarters of an inch for unpaved surfaces.
On a 12 foot driveway, half an inch per foot puts the center about 3 inches above the edges (6 ft x 1/2 in). Cut that shape into the soil underneath, because each layer follows the contour below it (Komplet America, Hunker). Every layer then stays the same thickness and the crown costs no extra stone. Slope the whole driveway away from buildings (Gravelshop).
Width
One car needs 10 to 12 feet. Two cars need 20 to 24 feet, with 18 as the tightest workable width (Concrete Network, Bovee’s). Check your town’s minimum before you dig.
Worked example: 12 ft by 60 ft
The area is 12 x 60 = 720 square feet. For each layer, multiply by the thickness in feet, divide by 27 for cubic yards, add 10 percent, then multiply by tons per cubic yard from this site’s density table: crushed stone 1.45, #57 1.4, crusher run 1.5.
| Layer | Net cubic yards | With 10% extra | Tons |
|---|---|---|---|
| Base, 6 in crushed stone | 13.33 | 14.67 | 21.27 |
| Middle, 3 in #57 | 6.67 | 7.33 | 10.27 |
| Top, 3 in crusher run | 6.67 | 7.33 | 11.00 |
| Total, 12 in | 26.67 | 29.33 | 42.53 |
Base: 720 x 0.5 ft = 360 cu ft, / 27 = 13.33 cu yd, x 1.10 = 14.67, x 1.45 = 21.27 tons. Middle and top: 720 x 0.25 ft = 180 cu ft, / 27 = 6.67 cu yd, x 1.10 = 7.33. Then 7.33 x 1.4 = 10.27 tons of #57 and 7.33 x 1.5 = 11.00 tons of crusher run.
Real stone varies. At the lowest and highest densities in the site’s table, the total runs from 37.8 to 49.1 tons. Clean #2 stone can weigh less than generic crushed stone, so ask your yard for its tons per cubic yard and rerun the weight in the cubic yards to tons converter.
The gravel calculator has no #2 stone, so run the base in the rock calculator with crushed stone, and the middle and top with the gravel calculator’s driveway presets. A 6 inch driveway in one layer of crushed stone is the base row alone: 14.67 cubic yards, 21.27 tons. For other sizes, try the cubic yard calculator.
What the stone costs
This site’s per ton prices are $10 to $50 for crushed stone, $22 to $75 for #57, and $12 to $45 for crusher run. On the 42.5 tons above that is about $570 to $2,330. At typical prices of $30, $40 and $27 per ton it is 21.27 x 30 + 10.27 x 40 + 11.00 x 27 = $638 + $411 + $297 = $1,346, or $1.87 per square foot. Fixr puts driveway materials at $1 to $3 per square foot and Bob Vila quotes $0.40 to $2 for the gravel, so a 12 inch build lands in the upper half. Delivery is extra, typically $75 per load.
Mistakes the sources warn about
- A thin base, or none (Port Aggregates, Hunker).
- Compacting one thick pile instead of lifts (Bovee’s, Hello Gravel).
- Skipping the compactor (Port Aggregates, Bovee’s).
- No crown, or a cupped surface (Hunker, Penn State).
- Leaving topsoil in the trench (Bob Vila, Gravelshop, Komplet America).
- Too little overlap at fabric seams, which Pro Fabric Supply calls the most common point of failure in DIY installs.
- A top layer of only fine gravel, which Port Aggregates says washes out.
Run each layer through the calculators before you call the yard.